Abstract:The management interface of DBB mode is numerous and the coordination is complex.When it is applied to overseas China-invested projects,the owner’s domestic management team will not adapt due to the significantly increased difficulty.The mode is not conducive to the comprehensive advantages of designers either.To avoid the disadvantages mentioned above,the new project management mode named “design and management integration with Chinese-foreign cooperation” and its organization are put forward,and it is concluded from the successful application of it in Abudhabi Khalifa Port container terminal phase Ⅱ that the new mode can give full play to the comprehensive advantages and enthusiasm of the designer in professional knowledge,communication skills and management. It can improve the coordination efficiency with governments,make all parties involved more closely,reduce internal consumption,and is very beneficial to the management of quality,progress and cost,and it is worthy of applying in similar projects.