深厚软土区大水深条件下筑斜坡堤对桩基的影响研究
DOI:
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:


Impact of sloping breakwater construction on pile foundations under deep water conditions in deep soft soil areas
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    针对深厚软土区、大水深条件下进行港口扩建工程时新建码头桩基位于斜坡堤内且临近既有码头结构带来的不利影响进行研究。依托马来西亚沙巴港扩建工程,选取典型不利断面,采用Plaxis软件建立精细有限元模型,重点研究斜坡堤施工对桩基的影响机制及优化控制措施。通过对比两种主要施工方案发现,桩基施工时机对新建码头桩基影响至关重要,选择在斜坡堤填筑完成并经历一定固结后再进行桩基施工能显著降低桩基的弯矩和水平位移,同时研究斜坡堤填筑时施工间歇期的影响,通过对比,确认45 d间歇期为较优的时间,能够较好地平衡工期和减少对桩基的不利影响。对临近既有码头的基槽开挖方案研究表明,控制基槽开挖深度(8 m)可以平衡好基槽自身稳定性和对既有结构的影响;通过控制桩基施工时间、施工间歇期、基槽开挖深度,可以有效地保障新建与既有桩基的安全,并控制工程成本。

    Abstract:

    This paper investigates the adverse impacts associated with new wharf piles constructed within a sloping breakwater in close proximity to existing wharf structures during port expansion projects under conditions of deep soft soil deposits and significant water depth.Taking the Sabah Port expansion project in Malaysia as a case study,a representative critical cross-section is selected,and a detailed finite element model is built by Plaxis software.Analyzing the influence mechanism of sloping breakwater construction on pile foundations and exploring optimized control measures is focused on.Comparative analysis of two primary construction schemes reveals that the timing of pile installation is crucial for the new wharf piles.Constructing the piles after the breakwater fill placement is complete and has undergone a certain period of consolidation significantly reduces pile bending moments and horizontal displacements.The effect of construction intervals during breakwater filling is also examined.Through comparative research,a 45-day interval is confirmed as a preferable duration,effectively balancing project schedule demands with minimizing adverse effects on the piles.Furthermore,research on the dredging scheme near the existing wharf indicates that controlling the dredging depth(8 m)effectively balances the stability of the dredged trench itself with the impact on the adjacent existing structure.The findings provide valuable insights for constructing sloping breakwaters near existing structures.By controlling the pile installation timing,implementing construction intervals,and regulating dredging depth,the safety of both new and existing pile foundations can be effectively ensured,while also controlling project costs.

    参考文献
    相似文献
    引证文献
引用本文

王光健,胡小波,贾 涛,等.深厚软土区大水深条件下筑斜坡堤对桩基的影响研究[J].水运工程,2025(9):222-232.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2025-09-16
  • 出版日期:
文章二维码