某枢纽省水船闸输水系统水力学模型试验
DOI:
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:


Hydraulic model test of filling and emptying system for a water-saving ship lock
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    某枢纽船闸所处航道沿线水资源匮乏,且船闸一次输水过程耗水量大,船闸需带省水功能。根据船闸最大工作水头及闸址地形条件,提出采用带1个省水池的短廊道集中输水系统布置方案。为解决省水船闸设计中的输水系统布置的水力学关键技术难题,通过采用1:30物理模型,对船闸非省水运行和省水运行时的输水系统水力特性、船舶(队)停泊条件进行了试验研究。结果表明:采用的输水系统布置合理可行,各项输水水力指标满足规范和设计要求。

    Abstract:

    Due to the channel that a ship lock located is lack of water resources,and the water consumption of one filling and emptying process is large,the ship lock should have water-saving function.According to the maximum difference between water level and the topographic conditions of the lock site,we propose a short-culvert filling and emptying system with a water-saving pool.To solve the key hydraulic problems of the filling and emptying system layout during the design of water-saving ship lock,we test the hydraulic characteristics and berthing conditions during lock filling and emptying with non-water-saving and water-saving operations by lock physical model with a scale of 1:30.The results show that the layout of the filling and emptying system is reasonable and feasible,and the hydraulic characteristics meet the specifications and design requirements.

    参考文献
    相似文献
    引证文献
引用本文

韩莹莹,刘海民,张丽媛,等.某枢纽省水船闸输水系统水力学模型试验[J].水运工程,2023(3):121-126.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2023-03-14
  • 出版日期:
文章二维码