特殊条件下超等级船舶系泊设计与实践
DOI:
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:


Design and practice of super-class ship mooring facilities under special conditions
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    巴基斯坦某项目受工期和自然条件影响,卸船机整机上岸必须在码头尚未完工的特定窗口期进行,且卸船机运输船舶等级远超码头设计船型,需布置临时系泊设施。针对码头系泊设施,开展了一系列比选和研究工作,用数值模拟软件分析船舶在风、浪、流综合作用下的系缆力情况,提出一种可快速组装和拆除的重力式临时系锚结构并付诸实施。工程实践表明,该系统具有可靠性高、经济性好、施工方便的优点。

    Abstract:

    Because a certain project in Pakistan is affected by the construction period and natural conditions,the whole unit unloading must be carried out in the specific window period when the wharf has not been completed,and the ship type used for transporting the ship unloader is far beyond the designed ship type of the wharf,so temporary mooring facilities need to be arranged. In this paper,a series of comparison and research work are carried out to analyze the mooring force of ships under the combined action of wind,wave and current by numerical simulation software,and a temporary gravity mooring scheme which can be quickly assembled and dismantled is proposed and put into practice. The engineering practice shows that the system has the advantages of high reliability,good economy and convenient construction.

    参考文献
    相似文献
    引证文献
引用本文

张翠莹,陈 磊,王君辉.特殊条件下超等级船舶系泊设计与实践[J].水运工程,2023(1):57-63.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2023-01-12
  • 出版日期:
文章二维码