Water retaining engineering measures during construction period of Qianwei ship lock gravity lock wall
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    岷江犍为航电枢纽施工任务重、时间紧。为缩短施工工期、节省围堰的施工投资、满足枢纽工程整体进度计划及施工期通航要求,需拆除二期二段围堰,并在汛期利用船闸外侧重力式闸墙挡水继续施工。针对汛期利用船闸外闸墙挡水时结构的安全稳定问题,通过对不同挡水部位结构进行复核计算,提出相应的工程措施,满足结构安全稳定要求,确保犍为船闸施工工期并节省工程投资。

    Abstract:

    The construction task of Qianwei navigation-power junction on Minjiang River is heavy and the time is short. In order to shorten the construction period,save the investment of cofferdam construction,and meet the overall schedule of the project and the navigation requirements during the construction period,it is necessary to remove the “second stage and second section cofferdams”,and use the gravity lock wall outside the ship lock to retain water during the flood season to continue construction. In view of the safety and stability of the structure when the external lock wall is used for water retaining in flood season,the paper puts forward the corresponding engineering measures by rechecking and calculating the structures of different water retaining parts,so as to meet the safety and stability of the structure,ensure the construction period of Qianwei ship lock,and save the project investment.

    参考文献
    相似文献
    引证文献
引用本文

周定科,李泳龙,吴礼国.犍为船闸重力式闸墙施工期挡水工程措施[J].水运工程,2021(12):94-98.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2021-12-06
  • 出版日期:
文章二维码