Design optimization of deepwater breakwater for refinery & chemical integration supporting crude oil terminal project
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    某炼化一体化项目配套原油码头工程深水防波堤所处海域自然条件复杂,通过数值模拟,重新推算设计波浪要素。由于原设计波浪要素取值较低,防波堤在施工过程中遭受台风破坏。根据新的设计波浪要素和新实施的规范,提高防波堤设计标准,优化防波堤设计方案。经物理模型试验验证,采取超大型扭王字块护面和新型双层扭王字块护面结构是可行的,可供类似工程设计参考借鉴。

    Abstract:

    The deepwater breakwater for a refinery & chemical integration supporting crude oil terminal project locates at waters with complicated natural conditions. So,we recalculate the design wave elements by numerical simulation. Because the original design wave elements’ values are small,the breakwater was damaged by typhoon in the process of construction. According to the new design wave elements and newly implemented codes,we improve the design standard of the breakwater and optimize its design scheme. The physical model tests verifies that it is feasible to adopt the super-large accropode and the new-type double-layer accropode armor structure,which may serve as reference for similar engineering design.

    参考文献
    相似文献
    引证文献
引用本文

陈海龙,文君锋,武 政,等.某炼化一体化项目配套原油码头工程深水防波堤设计优化[J].水运工程,2020(9):97-102.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2020-09-02
  • 出版日期:
文章二维码