    摘要:

    建在海洋环境中的高桩码头,桩基础改变了水质点移动的路径和水流剪切力,可能产生海床土颗粒的运移或冲刷,这样的冲刷会给结构和基础的稳定性带来威胁。采用国内外5种常用公式,对高桩码头局部冲刷进行计算,并与工程的实测值进行对比分析。结果表明,将波浪和潮流进行叠加,得到波流共同作用的流速,再运用韩海骞和J&S公式计算拟建工程区的桩柱局部冲刷深度是可行的。

    Abstract:

    The pile foundation of high-piled wharf built in the marine environment changes the original path of water particle movement and the shear force of water flow,which can cause the movement or scour of soil particles on the seabed.The scour is a threat to the stability of the structure and foundation.This paper calculates the local scour of high-piled wharf by five commonly used formulas at home and abroad,and compares with the measured values of the project.The results show that the wave and tidal current are superposed to get the velocity of the wave-current interaction,and it is feasible to calculate the local scour depth of piles in the proposed project area by using the formulas of Han Haiqian and J & S.

    参考文献
    相似文献
    引证文献
引用本文

刘 嫔.高桩码头桩基局部冲刷研究[J].水运工程,2020(8):100-102.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2020-08-12
  • 出版日期:
文章二维码