宁波舟山港穿山港区铁路进港整体改造平面布置
DOI:
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:


General layout of reconstruction due to entrance rail line of Chuanshan port area at Ningbo Zhoushan Port
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    针对铁路线进港所引起港区已建设施改造的问题,基于对规划铁路线进港区域现状以及港区运营需求的分析,遵循“保障港区营运,尽可能不占用现有堆场,对已建设施影响最小化”的原则,围绕铁路进线后所引起的港区整体改造平面布局形态进行技术、经济研究和比选,并提出推荐方案3,为打造宁波舟山港大型铁矿石海铁联运枢纽奠定基础。

    Abstract:

    In view of the problem of the reconstruction of existing facilities caused by the entry of railway lines,and based on the analysis of the current status of the planned railway line entry area and the operational needs of the port area,we make a technical and economic comparison of the overall layout of the port area caused by the entry of the railway to the port area.Following the principle of “ensuring the operation of the port area,not occupying the existing yard as far as possible,and minimizing the impact on existing facilities”,we propose the recommended scheme 3,which lays a foundation for building a large-scale iron ore sea-rail intermodal transport hub in Ningbo Zhoushan Port.

    参考文献
    相似文献
    引证文献
引用本文

戴 进,叶宇旻.宁波舟山港穿山港区铁路进港整体改造平面布置[J].水运工程,2019(7):93-98.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2019-07-12
  • 出版日期:
文章二维码