大型沉箱气囊顶升及出运施工技术
DOI:
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:


Large caisson air bag’s jacking and transportation construction technology
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    针对某矿石码头大型沉箱体积大、超重、既有沉箱预制台座限制、无法采用传统方法用气囊一次性顶升的问题,采用不同时顶升的新方法——通过调整沉箱底部气囊充气压强,可以实现沉箱的前后交替顶升。该方法中气囊不用全部处于超高压状态,可以较快速达到气囊充压要求,对充气设备要求不苛刻,施工更易操作、更安全,可为大型沉箱施工提供借鉴。

    Abstract:

    Aiming at the problem of large caisson volume,overweight weight and precast caisson pedestal in an ore wharf,the traditional method of using air bag to jack up at one time can not be adopted.By adopting a new method of jacking up at the same time,the problem of insufficient air bag jacking and inability to jack up large and overweight caisson is solved.The results show that by adjusting the aeration pressure of the air bag at the bottom of the caisson,alternate jacking up of the caisson before and after can be achieved.By this method,the air bag need not to be in the state of super-high pressure,and it can meet the filling pressure requirements of the air bag relatively quickly.It can be used as reference for the large-scale caisson construction.

    参考文献
    相似文献
    引证文献
引用本文

赵宪良,李超超,赵海丰.大型沉箱气囊顶升及出运施工技术[J].水运工程,2019(5):209-212.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2019-05-15
  • 出版日期:
文章二维码