Penetration performance of thin-wall steel pipe pile through highly weathered rock
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    结合东非某工程12 mm壁厚钢管桩沉桩实践,总结薄壁钢管桩在强风化岩层的沉桩规律,得出以下结论:钢管桩进入标贯击数50击的强风化珊瑚石灰岩面时,其贯入度为21.5~28.3 mm击。桩尖位于强风化岩层时液压锤能量传递系数最大可达94.5%,薄壁钢管桩进入强风化珊瑚石灰岩持力层最深可达7.1 m,此时贯入度为1.5 mm击。基桩D1和E1高应变结果显示,薄壁钢管桩桩尖进入强风化岩层3.7 m时,端阻力值增加明显趋缓,此时比刚入岩端阻力值增加30.8%~32.8%。

    Abstract:

    Based on the piling practice of 12 mm thick steel pipe pile in a project in the Eastern Africa,we summarize the pile-driving regularity of the thin-wall steel pipe pile in the highly weathered rock area and the conclusions are as follows:when the steel pipe pile enters the highly weathered rock of 50 standard penetration blow count,the penetration is within 21.5~28.3 mmblow and the maximum energy transfer coefficient reaches 94.5% of the hydraulic pile driving hammer while the pile tip is in the highly weathered rock.The penetration depth of pile tip can reach 7.1 m in the highly weathered rock,and the penetration is 1.5 mmblow correspondingly.When the pile tip of the thin-wall steel pipe pile enters 3.7 m below the highly weathered rock layer,the end resistance increases slowly,and the resistance value of the pile increases by 30.8%~32.8% according to the result of pile D1 and E1.

    参考文献
    相似文献
    引证文献
引用本文

冯光华,吴青华,陆治周,等.薄壁钢管桩强风化岩层穿透性能研究[J].水运工程,2017(12):228-231.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2017-12-12
  • 出版日期:
文章二维码