    为有效利用疏浚土并与港区陆域形成工程相结合,连云港港30万吨级航道一期工程中共建设了长约18 km的配套围堤,围堤结构为爆破挤淤堤与充填袋斜坡堤组合。因此在工程中势必要处理好爆破挤淤堤与充填袋斜坡堤两种不同结构的衔接。介绍在连云港港30万吨级航道一期工程中爆破挤淤堤与充填袋斜坡堤的衔接处理方案,以及结合衔接方案的龙口布置方案。

    Abstract:

    In order to effectively use and integrate dredged materials into the port land formation works,a supporting dike of about 18 km long had been constructed in the Phase I of 300,000 DWT navigation channel development works at Lianyungang Port.The dike structure was made up of toe-shooting riprap dike and sandbag sloping dike,so these two different types of structure had to be connected properly during construction.This paper introduces the design solution of the connection between these two dikes as applied in the Phase I channel works,and accordingly presents the closure gap arrangement as well.

    参考文献
    相似文献
    引证文献
引用本文

蔡 军,张林海,侯海伟,等.爆破挤淤堤与充填袋斜坡堤衔接方案[J].水运工程,2017(11):172-175.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2017-11-17
  • 出版日期:
文章二维码