高桩码头构件吊装新技术
DOI:
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:


New technology of components installation in piled wharf
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    在高桩码头预制构件安装中,传统工艺一般都采用起重船施工。在某些工程中,天气恶劣、海况复杂,在利用起重船安装时,受风浪等因素的影响,施工进度缓慢,配套船机投入大、利用率低、成本大,安全风险高。主要介绍一种码头预制构件吊装技术,转水上施工为陆上施工。采用该技术安装码头预制构件,作业时间长,安装速度快,风险小,精度高,造价低,在外海无掩护海域作业时尤为明显。

    Abstract:

    In installation of prefabricated members of high-pile wharf,the floating crane is used traditionally. In some projects with bad weather and complex sea condition,by installation by floating crane faces many problems,such as slow installation,great investment of supporting ships and machines,low utilization rate,great cost and safety risks. This article introduces a dock prefabricated hoisting technique,which changes the water construction to the land construction,and which has the advantages of quick installation,less risks,high accuracy and low cost,and thus is especially advantageous in unsheltered sea area.

    参考文献
    相似文献
    引证文献
引用本文

缪晨辉,曾 晖,王晓光.高桩码头构件吊装新技术[J].水运工程,2016(2):176-180.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2016-02-03
  • 出版日期:
文章二维码