Effect analysis of channel regulation project from Jiulongpo to Chaotianmen in upper reaches of the Yangtze River
Author:
  • Article
  • | |
  • Metrics
  • |
  • Reference
  • |
  • Related [20]
  • | | |
  • Comments
    Abstract:

    After the 175 m water storage operation of the Three Gorges project,the scale of Jiulongpo to Chaotianmen reach cannot meet planning requirements.During the sedimentation period,the sediment is washed up and down,and the erosion is not timely,causing shallow navigation obstruction in the channel.The channel regulation of this reach is carried out from 2016 to 2020 to improve the channel scale of the engineering reach and curb the adverse development of channel conditions.After the completion of the project,the improvement effect is analyzed through regular observation.The results show that the river regime in the engineering reach is stable,the scale of the channel is significantly improved,and the unfavorable development trend is curbed,resulting in effective improvement of the channel conditions,achieving the goal of channel regulation.

    Reference
    [1] 长江重庆航运工程勘察设计院.长江上游九龙坡—朝天门河段航道建设工程工程可行性研究报告[R].重庆:长江重庆航运工程勘察设计院,2014.
    Chongqing Shipping Engineering Survey and Design Institute of the Yangtze River.Feasibility study report on the channel construction project from Jiulongpo to Chaotianmen in the upper reaches of the Yangtze River[R].Chongqing:Chongqing Shipping Engineering Survey and Design Institute of the Yangtze River,2014.
    [2] 刘德春,李龙成,程平,等.重庆主城区河段河床边界条件研究[J].人民长江,2007(9):132-135.
    LIU D C,LI L C,CHENG P,et al.Research on the boundary conditions of riverbeds in the main urban area of Chongqing[J].Yangtze River,2007(9):132-135.
    [3] 刘怀湘,陆永军,左利钦,等.三峡变动回水区重点河段演变分析[J].水利水运工程学报,2011(4):32-38.
    LIU H X,LU Y J,ZUO L Q,et al.Fluvial morphology study on key channels of the Three Gorges fluctuating back water area[J].Hydro-science and engineering,2011(4):32-38.
    [4] 赵志舟,赵世强,许光祥.山区河流滩群河段的碍航特征与整治原则分析[J].水利水运工程学报,2013(2):39-44.
    ZHAO Z Z,ZHAO S Q,XU G X.Analysis of navigation hindering characteristics and regulation principle of shoal group reaches of mountain rivers[J].Hydro-science and engineering,2013(2):39-44.
    [5] 许全喜,袁晶,董炳江.长江泥沙变化及河床冲淤研究[J].长江技术经济,2019,3(3):58-68.
    XU Q X,YUAN J,DONG B J.Sediment change and river bed erosion and deposition in the Yangtze River[J].Technology and economy of Changjiang,2019,3(3):58-68.
    [6] 何艳军,张璠.三峡水库变动回水区泥沙冲淤特性分析[J].水道港口,2010,31(5):473-477.
    HE Y J,ZHANG F.Characteristics of scouring and deposition in fluctuating backwater region of the Three Gorges reservoir[J].Journal of waterway and harbor,2010,31(5):473-477.
    [7] 胡春宏.三峡水库175m试验性蓄水十年泥沙冲淤变化分析[J].水利水电技术,2019,50(8):18-26.
    HU C H.Analysis on sediment scouring and silting variation of Three Gorges Reservoir since 175 m trial impoundment for past ten years[J].Water resources and hydropower engineering,2019,50(8):18-26.
    [8] 陈贤祎.新水沙条件下三峡水库重庆河段泥沙淤积与航道整治研究[D].重庆:重庆交通大学,2009.
    CHEN X Y.The sedimentation and regulation of the Chongqing reach of the Three Gorges Reservoir under the condition of newseiries of water and seniment[D].Chongqing:Chongqing Jiaotong University,2009.
    [9] 长江重庆航运工程勘察设计院.长江上游九龙坡—朝天门河段航道建设工程初步设计[R].重庆:长江重庆航运工程勘察设计院,2015.
    Chongqing Shipping Engineering Survey and Design Institute of the Yangtze River.Preliminary design of the channel construction project from Jiulongpo to Chaotianmen in the upper reaches of the Yangtze River[R].Chongqing:Chongqing Shipping Engineering Survey and Design Institute of the Yangtze River,2015.
    [10] 长江重庆航运工程勘察设计院.长江上游九龙坡—朝天门河段航道建设工程施工图[R].重庆:长江重庆航运工程勘察设计院,2015.
    Chongqing Shipping Engineering Survey and Design Institute of the Yangtze River.Construction drawing for the channel construction project from Jiulongpo to Chaotianmen in theupper reaches of the Yangtze River[R].Chongqing:Chongqing Shipping Engineering Survey and Design Institute of the Yangtze River,2015.
    [11] 长江重庆航道局.长江上游九龙坡—朝天门河段实船试航试验报告[R].重庆:长江重庆航道局,2021.
    Changjiang Chongqing Waterway Bureau.Report on the actual ship trial voyage test of the section from Jiulongpo to Chaotianmen in the upper reaches of the Yangtze River[R].Chongqing:Changjiang Chongqing Waterway Bureau,2021.
    Cited by
    Comments
    Comments
    分享到微博
    Submit
Get Citation

HE Yanjun. Effect analysis of channel regulation project from Jiulongpo to Chaotianmen in upper reaches of the Yangtze River[J]. Port & Waterway Engineering,2025(2):164-171.

Copy
Share
Article Metrics
  • Abstract:227
  • PDF: 241
  • HTML: 0
  • Cited by: 0
History
  • Online: February 10,2025
Article QR Code