Water retaining engineering measures during construction period of Qianwei ship lock gravity lock wall
DOI:
CSTR:
Author:
Affiliation:

Clc Number:

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    The construction task of Qianwei navigation-power junction on Minjiang River is heavy and the time is short. In order to shorten the construction period,save the investment of cofferdam construction,and meet the overall schedule of the project and the navigation requirements during the construction period,it is necessary to remove the “second stage and second section cofferdams”,and use the gravity lock wall outside the ship lock to retain water during the flood season to continue construction. In view of the safety and stability of the structure when the external lock wall is used for water retaining in flood season,the paper puts forward the corresponding engineering measures by rechecking and calculating the structures of different water retaining parts,so as to meet the safety and stability of the structure,ensure the construction period of Qianwei ship lock,and save the project investment.

    Reference
    Related
    Cited by
Get Citation

周定科,李泳龙,吴礼国.犍为船闸重力式闸墙施工期挡水工程措施[J].水运工程,2021,(12):94-98

Copy
Share
Article Metrics
  • Abstract:
  • PDF:
  • HTML:
  • Cited by:
History
  • Received:
  • Revised:
  • Adopted:
  • Online: December 06,2021
  • Published:
Article QR Code