Abstract:The wharf construction has many problems in Latin America and Africa,such as lack of large-scale ship equipment and poor offshore construction conditions(long-period wave).Meanwhile,the operation of conventional piling and the installing of prefabricated components are both difficult.Based on the general structure of pile wharf,we optimize design and construction of the structure,adopt a self-traveling platform by cantilever construction method,use the pile foundation as supporting structure,and also adopt composite beams and slabs.The method transforms the construction into activities on land as an innovation,establishes a new structure as wharf with pile foundation under cantilever construction method,avoids lack of large-scale ship equipment and poor offshore construction conditions(long-period wave).The method shows its well economical efficiency and applicability in meizoseismal area.