Abstract:The steel sheet pile structure was adopted in Israel Ashdod port staging harbor. Since the anchor sheet pile construction was at the hydraulic reclamation area,the construction facilities faced a safety risk due to the ununiform soil pressure on both sides of the sheet pile and sand liquefaction,deviation occurred during restricking construction.Taking measures including controling the head of reclamation pipe,storing sand with temporary dam,and increasing reclamation area and reserving sheet pile deviation,etc.,we solved related problems concerning safety and technology,and ensured the construction schedule of the anchor sheet pile.