Construction technology of single large T-girder
DOI:
CSTR:
Author:
Affiliation:

Clc Number:

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    Taking the crest rail beam installation in the navigation-power junction discharge sluice in Xiangjiang river for example,we analyze the installation environment and possible installation mode of the crest beam,and establish a comprehensive installation mode,i.e.homemade hydraulic lifting equipment and erection of beam transportation channel successful,by which we fulfill the installation of the single track beam smoothly.

    Reference
    Related
    Cited by
Get Citation

邢红梅,于忠强.单线大型T梁架设施工技术[J].水运工程,2015,(8):102-105