Application of integrated prefabrication and installation of abutments in offshore platform construction
DOI:
CSTR:
Author:
Affiliation:

Clc Number:

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    During construction of the permanent offshore platform in Jiangsu offshore observation platform project, to counter the extremely harsh weather condition,we carry out an optimization of the conventional construction scheme for the abutment and the observation house,and adopt the construction technology of integral prefabricating on land and installing at sea,by which the construction period of the main part of the project is greatly shortened .The optimized construction technology may serve as reference for similar projects concerning the offshore platform engineering.

    Reference
    Related
    Cited by
Get Citation

ZOU Feng, LIU Peng. Application of integrated prefabrication and installation of abutments in offshore platform construction[J]. Port & Waterway Engineering,2015(8):78-80.

Copy
Share
Article Metrics
  • Abstract:
  • PDF:
  • HTML:
  • Cited by:
History
  • Received:
  • Revised:
  • Adopted:
  • Online: August 12,2015
  • Published:
Article QR Code