Abstract:Affected by the level 5 & 6 clay soil of Lianyungang Ganyu port area phase I project,the operation of CSD is rather difficult.Focusing on the CSD’s dredging methods and transportation theory,we solve relevant problems by changing the mud thickness,cut footage,concentration,as well as the flow velocity.