    Based on the construction of anchor socketed piles for the 450 000 t crude terminal of Daxie, we discuss series of construction methods and technology, containing the stabilization of anchor socketed piles, the protection of pile tips, the erection of the drilling platform and the construction of rock anchoring, etc., all of which provide references for similar projects.

    Reference
    Related
    Cited by
Get Citation

黄卫明,方州恩.大榭45万t原油码头锚岩桩施工技术[J].水运工程,2012,(9):186-189