Construction technique of foundation pit for dockhead in Tianjin port ship building-repairing base
DOI:
CSTR:
Author:
Affiliation:

CCCC First Harbor Engineering Co., Ltd., Tianjin 300456, China

Clc Number:

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    The foundation of Tianjin harbor building-repairing base is unstable, the pressure head is high,and the excavation depth of the dockhead reaches 18.2m. This paper describes the stability analysis and excavation implementation of the foundation pit for the dockhead. The practice proves that it is effective to adopt higher construction surface pile follower, dewatering of foundation pits, pieced small -area excavation and timely construction of the upper structure. It may serve as a reference for similar projects.

    Reference
    Related
    Cited by
Get Citation

耿耀民,梁鼎明.天津临港造修船基地坞首基坑开挖施工技术[J].水运工程,2011,(07):174-179