    针对高桩码头升级改造工程对原码头结构应如何有效利用的问题,以上海港罗泾港区集装箱码头改造一期工程为依托,提出原码头结构综合利用的原则及重点问题,对原结构利用时与现有规范的符合性、剩余使用寿命的判断方式、新老混凝土交界面的处理方式等问题进行了分析研究。提出改造时总图、工艺与水工结构综合解决问题的思路,列出了改造时利用原结构的多个可行的技术路线。得出总体结论:宜主要按照当年设计时规范复核结构构造要求,结构剩余寿命应以检测评估方式确定;在平面布局中将3个原有码头布置于荷载较小的行车通道位置,采用了轻型设备减小岸桥荷载约20%;经实践可采用常规工法实现原结构拆除重建、补充桩基加固原结构、码头高程加高0.2~1.6 m、引桥增加排架和更换面板、原结构下方新建水电管线路由等技术路线。

    Abstract:

    Aiming at the problem of how to effectively utilize the original terminal structure in the upgrading and reconstruction project of high pile wharf,based on the phaseⅠcontainer terminal renovation project in Luojing port area of Shanghai Port,the principles and key issues of comprehensive utilization of the original terminal structure are put proposed.The compliance of the original structure with existing specifications,the judgment method of remaining service life,and the treatment method of the interface between new and old concrete are analyzed and studied.This paper proposes a comprehensive solution to the problems of general layout,process,and hydraulic structure during renovation,and lists multiple feasible technical routes for utilizing the original structure during renovation.The general conclusions are that it is advisable to mainly review the structural construction requirements according to the design specifications of the current year,and the remaining life of the structure should be determined through testing and evaluation.The project willThree original wharves are arranged in the plan layout at the location of the less loaded driving channel,and lightweight equipment is used to reduce the load on the quay crane by about 20%.Through practice,conventional construction methods can be used to achieve technical routes such as dismantling and rebuilding the original structure,reinforcing the original structure with supplementary pile foundations,raising the dock elevation by 0.2-1.6 m,adding scaffolding and replacing panels to the approach bridge,and constructing new water and electricity pipeline routes under the original structure.

    参考文献
    相似文献
    引证文献
引用本文

刘国宝,沈树茂,苑 艺.罗泾集装箱码头改造对原码头的综合利用方案[J].水运工程,2025(S1):82-89.

复制
分享
相关视频

文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2025-12-18
  • 出版日期:
文章二维码
0