肯尼亚Naivasha ICD主箱场与铁路作业线近远期平面布置
DOI:
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:


Short-term and long-term general layout between main container yard and railway line of Naivasha ICD, Kenya
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    针对肯尼亚Naivasha ICD主箱场施工图设计过程中,近期须满足正面吊装卸标轨火车集装箱,远期须满足轨道式龙门起重机对标轨和米轨火车换装集装箱的问题,进行详细研究。通过分析近、远期功能需求和工程区域现状条件,结合地形地貌特点、排水及土石方的需求,统筹考虑多因素相互作用的影响,确定满足近远期功能需求且减少远期改造工程量的平面布置。研究成果可为同类型工程设计提供参考。

    Abstract:

    Aiming at the problem that the main container yard detailed design of Naivasha ICD in Kenya,it is necessary to meet the requirement of the reach stacker handling containers from standard gauge train in the short-term,and it is necessary to meet the requirement of the rail-mounted gantry cranes to convert standard gauge trains and meter gauge trains in the long-term,we carry out a detailed study. We analyze the short-term and long-term functional requirements and the current conditions of the project area,consider the interaction of multiple factors combining with the topographic and geomorphic characteristics,drainage and earthwork requirements,determine the general layout of the project,which can meet the short-term and long-term functional requirements and reduce the long-term reconstruction quantity. The results can provide references for similar projects.

    参考文献
    相似文献
    引证文献
引用本文

莫丽丽,徐俊东,陶元洪.肯尼亚Naivasha ICD主箱场与铁路作业线近远期平面布置[J].水运工程,2021(10):74-77.