Study on navigation during construction period of Yakou hydro-junction in Hanjiang River
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    汉江雅口航运枢纽为通航河流枢纽,工程施工期应妥善处理船舶通航问题。结合工程分期施工的方案,提出对应的通航方案,施工一期采用疏挖后的束窄河道作为临时航道通航,避免断航带来的不利影响;施工二期采用已建船闸通航,实现临时通航与永久建筑物的结合。针对施工期通航水流条件问题,采用数值模拟计算方法,建立二维水动力数值模型对各流量工况下的水流流态进行计算分析。结果表明,两阶段施工期的通航水流流速均满足相关要求。

    Abstract:

    Yakou hydro-junction in Hanjiang River is navigable river junction.The navigation problem should be properly dealt with during the construction period.We propose corresponding navigation scheme combined with phased construction scheme, adopt the narrow channel in the first construction period so as to avoid the adverse effects caused by the broken navigation, and use the established lock in the second period to realize the combination of temporary navigation and permanent building.In view of the navigable flow conditions during the construction period, we establish a two-dimensional hydrodynamic numerical model to calculate and analyze the flow pattern under various flow conditions.The results show that the navigable flow conditions of two construction periods satisfy the related requirements.

    参考文献
    相似文献
    引证文献
引用本文

张信伟,孙保虎,胡峰军,等.汉江雅口航运枢纽工程施工期通航研究[J].水运工程,2020(12):155-160.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2020-12-14
  • 出版日期:
文章二维码