国外大型预制型沉箱吊装施工的吊耳设计
DOI:
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:


Design of lifting lug for hoisting construction of large pre-fabricate caisson in overseas projects
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    针对国外大型预制沉箱吊装施工的吊耳设计问题,结合工程案例对吊耳本体强度和局部混凝土强度进行验算,并提出大型预制沉箱吊运的技术要求。基于欧美规范,对吊耳局部混凝土的受压强度、抗崩裂强度、抗拔出强度、抗侧面爆裂强度和抗剪撬强度进行验算。结果表明,吊耳本体强度和局部混凝土强度验算的结果均满足要求。沉箱壁板作为薄壁结构,吊耳局部混凝土强度应是设计的关键问题,且在吊装施工过程中应采取必要的措施来保证吊耳受力合理。

    Abstract:

    Aiming at the design issues of lifting lug for large pre-fabricated caisson hoisting construction,we verify the strength of lifting lug and local concrete combining with oversea marine project,and propose the technical specifications for hoisting.Based on the European and American codes,we verify the strength of local concrete including compression strength,breakout strength,pullout strength,side-face blowout strength and pry out strength.The results show that the strength of lifting lug and local concrete satisfy the requirements.The strength of local concrete is the key problem in the design of the caisson wall as a thin-walled structure.In the process of hoisting construction,necessary measures should be taken to ensure that the lifting lug bears reasonable force.

    参考文献
    相似文献
    引证文献
引用本文

李少斌,许建武,丁建军.国外大型预制型沉箱吊装施工的吊耳设计[J].水运工程,2020(6):214-219.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2020-06-08
  • 出版日期:
文章二维码