超大型扭王字块取消配筋的可行性
DOI:
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:


Feasibility of removing the steel rebar of super-large accoropode
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    港口建设不断向深水区域发展,在自然条件恶劣的海域建造防波堤时,护面块体的质量不断加大,通常采用配筋以增强其抗裂能力。为解决超大型扭王字块因配筋引起的预制施工困难,通过添加抗裂纤维替代配筋的方法予以解决。采用模型试验、理论计算和数值模拟方法,分析了扭王字块预制、吊运过程中的开裂风险,论证了超大型扭王字块取消配筋的可行性。

    Abstract:

    The port construction is continuously developing towards the deep-water area.When the breakwaters are built in the sea area with poor natural conditions,the mass of protection block is increasing,and the steel bar is usually used to enhance its anti-cracking ability.In order to solve the precast construction difficulty of super-large accoropode caused by the reinforcement,we add anti-cracking fiber instead of reinforcement.By model test and theoretical calculation and numerical simulation method,we analyze the cracking risk of super-large accoropode in prefabrication and hoisting process.The results demonstrate the feasibility of removing the steel rebar of super-large accoropode.

    参考文献
    相似文献
    引证文献
引用本文

文君锋,陈海龙,武 政.超大型扭王字块取消配筋的可行性[J].水运工程,2018(9):191-197.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2018-09-14
  • 出版日期:
文章二维码