The construction technologies of side blasting and end blasting
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    为确保大连临空产业园填海造地工程北护岸爆炸挤淤施工质量,爆炸挤淤施工方式由全侧爆改为堤头爆。介绍了爆炸挤淤全侧爆及堤头爆两种施工技术,在相同条件下,针对施工质量、进度、成本进行了论述。比对分析得出:在爆炸挤淤堤身着底宽度与深度要求较高、无法通过一次侧爆形成堤身断面的情况下,宜优先考虑选用堤头爆爆炸挤淤施工

    Abstract:

    In order to ensure the construction quality of the north bank revetment of the reclamation project in Dalian airport industrial park,end blasting substitutes side blasting in the construction of the blasting and siltation.The construction technologies of side blasting and end blasting are introduced,and the construction quality,schedule and cost are discussed under the same conditions.By using the method of comparative analysis,it is concluded that it is necessary to give priority attention to selecte the end blasting in the case that the width and depth of body have high requirements by blasting silting removal method,and the body section cannot be taken shape through a side blasting.

    参考文献
    相似文献
    引证文献
引用本文

刘 旭,尹昆昆.爆炸挤淤全侧爆与堤头爆施工技术[J].水运工程,2017(S2):47-50.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2017-07-17
  • 出版日期:
文章二维码