Application of integral demolition technique for large-scale piled wharf
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    针对巴拿马科隆港集装箱码头(CCT)项目三期二阶段码头改扩建工程中高桩码头整体拆除施工船舶跨国调遣困难、项目工期紧以及传统水下切桩工艺效率低、风险高等难题,进行多种拆除工艺的对比研究,通过对传统绳锯导向架的改进及新型液压剪切桩的成功应用,形成了适用于陆上高桩码头拆除作业的成套工艺,为高桩码头的改扩建尤其是桩基拆除提供了新思路、新技术,为类似工程提供了借鉴。

    Abstract:

    To counter the difficulties in the integral demolition works of high-pile wharf for wharf reconstruction and extension engineering of Port of Panama Colon Container Terminal (CCT)Phase III Stage 2 Project,such as difficult transnational dispatching of construction ships,tight project schedule,low efficiency and high risk of the traditional underwater pile cutting technique,etc.,this paper carries out a comparative study on various demolition techniques.Through the improvement of the traditional wire saw guide frame and the successful application of the new-type hydraulic cutter in pile cutting works,a complete set of techniques applicable to on-land demolition works for high-pile wharf forms,which provides a new idea and new technology for the extension project of high-pile wharf,especially for pile foundation demolition works.It also offers reference for similar projects.

    参考文献
    相似文献
    引证文献
引用本文

孙合军,赵建明,随超越.大型高桩码头整体拆除工艺应用[J].水运工程,2017(9):117-120.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2017-09-15
  • 出版日期:
文章二维码