    摘要:

    结合某挖入式港池工程,介绍深水整体卸荷式板桩结构的超长钢管-板桩结合墙设计及关键施工工艺。根据辅桩适应变形的能力,对主桩垂直度允许偏差提出0.4%的要求。通过对导向架合理的设计和改造,采用整桩起吊、振打结合、交错下沉的沉桩工艺等措施,确保顺利沉桩。结果表明,全部钢管-板桩结合墙都达到设计高程,沉桩效果良好,可为类似工程提供技术参考。

    Abstract:

    Based on a dredged harbor basin project,this paper introduced the design and key construction technologies about the over-length steel tube-sheet pile wall in the integral deep-water unloading sheet-pile structure.According to the auxiliary pile’s ability to adapt to the deformation,the requirement that the allowable deviation of main pile’s verticality is no more than 0.4% was put forward.Through rational design and transformation to the guide frame,the pile-sinking technologies such as whole-pile lifting,vibrating-driving combination,and staggered sinking were adopted to ensure that the piles sink smoothly.The results show that all the steel tube-sheet pile walls achieve the design elevation and have a good pipe sinking effect.It can provide a technical reference for similar projects.

    参考文献
    相似文献
    引证文献
引用本文

蔡开程,宋成涛.深水板桩码头超长钢管-板桩结合墙设计与施工技术[J].水运工程,2016(8):168-173.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2016-08-18
  • 出版日期:
文章二维码