Calculation analysis and solution for exceeded install tolerance of block quay wall
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    依据安哥拉某重力式方块码头施工过程中发生的安装偏差超标的实例,根据海侧实测数据,利用静力计算、修正静力计算、有限元分析计算3个阶段的渐进过程分析偏差超标方块的受力情况,为后续工作的合理安排提供依据,在解决施工问题并保证进度方面具有普遍的参考意义。

    Abstract:

    Taking the exceeded deviations of block installation during construction of Angola certain gravity block type quay wall for example,according to the sea-side actual measurement data,and using three stages of gradual processes analysis including static calculation,amended static calculation,and finite element analysis,we analyze the stress of blocks exceeding the install deviation to provide a basis for the reasonable arrangement of the follow-up work,and serve as reference for solving the construction problem and ensure the construction progress as well.

    参考文献
    相似文献
    引证文献
引用本文

汪舟红,许伟群.方块码头安装偏差过大的计算分析及解决办法[J].水运工程,2016(3):66-73.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2016-03-17
  • 出版日期:
文章二维码