    摘要:

    武汉二七长江大桥北岸6 m×90 m副通航孔桥段位于长江Ⅲ级阶地,施工期水文地质情况变化剧烈,预定的钢套箱法基础施工工艺适应性受到了严重影响。基于对浅滩区桥梁基础施工常用围堰形式特点、适用性的分析,结合该工程实际,将基础施工工艺调整为钢板桩围堰法,达到提高施工效率、节约成本的目的。

    Abstract:

    The bridge section of 6 m×9 m on north secondary navigable span of Wuhan Erqi Yangtze River Bridge is located on the third terrace of the Yangtze River.As high variability in hydrogeological condition during construction period,the proposed construction method for the bridge foundation using steel boxed cofferdam is affected seriously.Based on the analysis of the form characteristics and applicability of common types of cofferdam in the shoal area and combining with the actual condition of the project,we adjust the construction method for the bridge foundation to steel sheet pile cofferdam to improve the construction efficiency and save the cost.

    参考文献
    相似文献
    引证文献
引用本文

孙 琦,孙晓伟,陈超华.浅滩区桥梁基础施工工艺[J].水运工程,2015(8):90-93.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2015-08-12
  • 出版日期:
文章二维码