武汉鹦鹉洲长江大桥2#桥墩局部冲刷防护设计
DOI:
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:


Anti-scouring design for pier No.2 of Yingwuzhou Yangtze River bridge
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    为防止武汉鹦鹉洲长江大桥2#桥墩建设对拟建的武桥水道航道整治工程建设和整治效果产生不利影响,提出将桥墩防护工程和其周边航道整治工程合二为一的设计方案,统筹安排施工进度,并根据建设过程中出现的问题,适时调整设计方案,解决了桥梁建设与航道整治工程之间的矛盾,确保两项工程保质、保量、按时竣工。

    Abstract:

    In order to prevent adverse effects of pier No.2 of Yingwuzhou Yangtze River bridge on the waterway regulation engineering of Wuqiao waterway,we integrat the engineering of the bridge pier protection engineering and its surrounding waterway regulation engineering,arrange comprehensively the construction schedule,and adjust the design scheme timely according to the problems in the construction process to deal with the contradiction between the bridge construction and waterway regulation engineering,and ensure that the two projects complete on time and with high quality.

    参考文献
    相似文献
    引证文献
引用本文

李文全,冯 刚,王志军,等.武汉鹦鹉洲长江大桥2#桥墩局部冲刷防护设计[J].水运工程,2014(12):142-146.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2014-12-18
  • 出版日期:
文章二维码