柳梓河综合码头工程对长江公安河段水文动力与河床演变的影响研究
DOI:
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:


Research on the impact of Liuzihe comprehensive wharf project on hydrodynamics and riverbed evolution of Gong’an reach of the Yangtze River
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    为深入研究柳梓河综合码头工程对长江干流公安河段水沙与河床稳定的影响,采用基于2021年实测地形的定床与动床河工模型试验,结合原型观测与2013—2020年共10 a水沙数据资料,模拟工程后10 a的演变过程,系统分析工程实施后的水流、水位、分流比及河床冲淤演变。结果表明:工程建设对河势整体影响微弱,范围仅限于工程区上下游5 km内,水位变幅小于0.03 m,近岸流速调整不超过0.04 m/s。柳梓河汉道分流比仅在流量大于22 000~24 000 m3/s时稍有增加(最大增幅0.10%)。在河床冲淤方面:进口段淤积最为显著,主航道疏浚区呈约3 a周期的“回淤-再平衡”过程,而港池则表现为显著的累积性淤积,10 a淤厚2.0~2.3 m。工程未改变整体河势,主航道3.8 m航槽保持稳定。研究揭示了工程区两种局部冲淤模式,并提出分期疏浚、动态监测与长期维护的策略。

    Abstract:

    To further investigate the impacts of the Liuzihe comprehensive wharf project on the flow-sediment characteristics and riverbed stability of the Gong'an Reach in the mainstream of the Yangtze River,fixed-bed and movable-bed physical model tests based on measured topographic data from 2021 are carried out.Combined with prototype observations and 10-year flow and sediment data from 2013 to 2020,the 10-year riverbed evolution process after project construction is simulated,and the variations in flow field,water level,flow division ratio,and riverbed erosion-deposition evolution after project implementation are systematically analyzed.The results show that the overall impact of project construction on the river regime is weak,with the influence scope limited to 5 km upstream and downstream of the project area.The water level variation is less than 0.03 m,and the near-bank flow velocity adjustments are no more than 0.04 m/s.The flow division ratio of the Liuzihe anabranch increases slightly only when the discharge exceeds 22,000-24,000 m3/s,with a maximum increase of 0.10%.In terms of riverbed erosion and siltation,the inlet section presents the most significant siltation;the main navigation channel dredging area exhibits a periodic “siltation-rebalancing” process with a cycle of approximately three years;the harbor basin suffers obvious cumulative siltation with a siltation thickness of 2.0-2.3 m over the 10-year period.The project does not alter the overall river regime,and the 3.8 m deep navigation channel remains stable.This study reveals two local erosion-deposition evolution modes in the project area and proposes targeted strategies,including phased dredging,dynamic monitoring and long-term maintenance.

    参考文献
    相似文献
    引证文献
引用本文

钟 利.柳梓河综合码头工程对长江公安河段水文动力与河床演变的影响研究[J].水运工程,2026(9):94-103.

复制
分享
相关视频

文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2026-09-17
  • 出版日期:
文章二维码